We are excited to present the following update:
- The concrete for the hangar’s floor has been poured as well most of the ramp that connects the hangar to the asphalt
- Approximately 95% of the underground items, such as sewer pipes, have been completed and the block work on the offices has started
- The electric and phone lines have been “roughed in” to the office area, communication room, and pump house
- Approximately 50% of the permanent fencing is up
Construction is moving ahead of schedule and will be completed for our January 2011 grand opening! Keep checking back for more updates as construction moves forward…